Only when we have finished with the installation do we remove the protective film which we recommend should be done within 15 days of completion.
Panels (PUR/PIR) must be protected from weather conditions (sun radiation, rain, ect) if not to be installed directly.
When unloading panels (PUR/PIR) from truck, extra care should be taken especially when using cranes with belts to avoid distortion of joint edges thus making fitting difficult.
Do not slide one panel (PUR/PIR) from another, but lift panels (PUR/PIR) as to avoid scratches and damages of the surfaces and immediate corrosion.